City of Stirling Corporate Business Plan

Outcome G4: Projects Service Improvement Planning

2019/20

2020/21

2021/22

2022/23

Q1 Q2 Q3 Q4

Seek quotations

Review of service levels, key performance indicators and identification of improvements to increase efficiency and effectiveness

Progress update to the Audit Committee Progress update to the Audit Committee Progress update to the Audit Committee

2019/20 project cost: $200,000

Workforce Plan

2019/20

2020/21

2021/22

2022/23

Deliver the initiatives outlined in the City’s Workforce Plan 2018 – 2022

Q1 Q2 Q3 Q4

Quarterly report to the Executive Team Quarterly report to the Executive Team Quarterly report to the Executive Team Quarterly report to the Executive Team

2019/20 project cost:$80,000

Cultural Development Plan

2019/20

2020/21

2021/22

2022/23

Implementation of initiatives to improve the City’s workplace culture

Q1 Q2 Q3 Q4

Culture working group report to the executive team Culture working group report to the executive team Culture working group report to the executive team Culture working group report to the executive team

2019/20 project cost: $100,000

Electronic Invoice Workflow Implementation

2019/20

2020/21

2021/22

2022/23

Q1 Q2 Q3

Project scoping and business requirements completed

The project is to revolutionise the way the City manages its processes associated with invoice and other paper documents

Product and vendor evaluation completed Tender process completed Vendor engaged and contract signed Project implementation commenced

2019/20 project cost: $228,761

Q4

Project implementation completed

Contract Management System Software Implementation 2019/20

2020/21

2021/22

2022/23

Q1

Vendor engagement and contract sign-off Project implementation commenced

The project will implement a contract lifecycle management system in the City, which will be a single centralised source for managing all contracts throughout their lifecycle

Q2 Q3 Q4

Project execution complete

Not applicable Not applicable

2019/20 project cost: $30,000

CIS Project Management Office Redesign

2019/20

2020/21

2021/22

2022/23

Q1 Q2 Q3 Q4

Stage one – foundation and high value activities

This project will improve the City’s IT project management capabilities through implementing recommendations from the ‘Re-imagining the PMO’ review

Stage two – building on maturity

Project implementation completed

Not applicable

2019/20 project cost: $130,000

SharePoint Development

2019/20

2020/21

2021/22

2022/23

To redesign and upgrade the City’s intranet site

Q1 Q2

Stage three release

Stage four release Stage five release and completion

2019/20 project cost: $100,000

Q3 Q4

Not applicable Not applicable

34