City of Stirling Corporate Business Plan

Outcome 1: Projects Oral History Interviews – Stirling Stories To conduct seven oral history interviews with senior residents of retirement centres and members of autumn and seniors’ clubs for recording the history of the local areas for future generations

Outcome 1: Projects Art and Award Exhibition 2021

2021/22

 2022/23

2023/24

2024/25

2021/22

 2022/23

2023/24

 2024/25

Q1 Methodology for Stirling Stories (oral history interviews) finalised Seven sites for the oral history interviews – one for each Ward selected Q2 Oral history interviews in sites 1 to 6 completed Q3 Oral history interview in site 7 completed Q4 Sound recordings of the interviews uploaded to the City’s website

This biennial exhibition is open to Western Australian artists to display their original 2D and 3D works in a public exhibition

Q1 Promotion of Art and Award Exhibition 2021 commenced Artists shortlisted Q2 Art and Award Exhibition 2021 event conducted Entries evaluated Awards announced

Q3 Q4

2021/22 net project cost

$70,000

2021/22 net project cost

$21,000

Bond Cottage Renovation

2021/22

 2022/23

2023/24

2024/25

Public Art Projects

2021/22

 2022/23

 2023/24

 2024/25

To utilise the historical Bond Cottage as a shop front for Stirling Men’s Shed

Q1 Bond Cottage relocated from the City of Stirling Works Depot to the Men’s Shed at 8 Vasto Place, Balcatta Q2 Site works at 8 Vasto Place, Balcatta completed

To implement the City’s Public Art Masterplan by installing one or more small art works in the public realm across the City

Q1 Project planning and scoping completed Q2 Artist’s brief developed Quotations for art works requested Q3 Quotations received and assessed, and artwork selected Q4 Artwork installation completed

Q3 Bond Cottage restoration commenced Q4 Bond Cottage restoration completed Shop front opened

2021/22 net project cost

$50,000

2021/22 net project cost

$20,000 Partially grant funded

Street Signs of Significance

2021/22

 2022/23

2023/24

2024/25

Community Collaboration Fund

2021/22

 2022/23

 2023/24

 2024/25

Q1 Selection criteria for local history information signage developed Street names selected Database listing of all streets, roads and laneways within the City of Stirling completed Q2 Research of the selected street names completed Q3 Signages installed Aboriginal street naming history and signages prioritised Q4

To provide historical information on the significance of the person or events after which streets are named Forty local history information signs will be attached to selected existing street name signs

To provide grants to community members, organisations and businesses to build their capacity and enable them to meet the City’s social planning objectives

Q1 Community Collaboration Fund program promoted Applications for grants invited Q2

Q3 Applications received and reviewed Q4 Fund acquittal and report completed

2021/22 net project cost

$50,000

Kaleidoscope Initiative

2021/22

 2022/23

 2023/24

2024/25

To create partnerships with new migrants and businesses to build a skilled and diverse workforce

Q1 Mentoring cycle 1 (2021/22) commenced

2021/22 net project cost

$20,000

Work-Integrated Learning Program cycle 1 (2021/22) commenced Customer relationship management (CRM) tool developed Q2 Graduation of mentees/Work-Integrated Learning Program Mentoring cycle 2 (2021/22) commenced Toolkit and assessment for inclusive workplaces developed Q3 Report submitted to the Office of Multicultural Interests Work-Integrated Learning Program cycle 2 (2021/22) commenced Graduation of mentees Q4 Graduation of mentees/Work-Integrated Learning Program Work-Integrated Learning Program cycle 3 (2021/22) commenced

2021/22 net project cost

$89,312 Partially grant funded