City of Stirling Corporate Business Plan

Projects

2023/24

2024/25

2025/26

2026/27

Hamersley Public Golf Course Redevelopment

Development of the golf pavilion into a modern facility providing a wide range of golf activities and a two-level automated driving range

Q1 Contract awarded Q2 Demolition of existing pavilion completed Construction of golf pavilion and driving range commenced Q3 Blockwork for golf pavilion completed Q4 Civil structure for golf pavilion and driving range completed

$Nil Reserve funded

2023/24 budget

2023/24

2024/25

2025/26

2026/27

Redevelopment of Stirling Leisure Centres – Terry Tyzack Aquatic Centre – Inglewood Redevelopment to include a new outdoor changeroom facility, design of geothermal heating and centralised administration and reception area

Q1 Ceramic tiling completed, plumbing services installed Installation and commissioning of plant equipment Q2 Final fit-off and pool commissioning Practical completion and opening of outdoor pools Q3 Q4 Minor entrance works, landscape upgrades Stage 3 design complete, including geothermal heating and splashpad

2023/24 budget

$1,105,000

2023/24

2024/25

2025/26

2026/27

Sportsfields Sustainability Renovation

Improve the standard of turf surfaces for the City’s high-use sports fields and playing surfaces

Q1 Comprehensive renovation program developed Q2 Spring renovation program completed Q3 Q4 Autumn renovation program completed Project evaluation completed

2023/24 budget

$986,314

2023/24

2024/25

2025/26

2026/27

Stirling City Centre

Develop a Land Staging Plan for Stirling City Centre

Q1 Consultation with the Public Transport Authority for bus lanes commenced Q2 Land Staging Plan reported to Council Q3 Report on Hertha Road remediation scoping study presented to Council Q4

2023/24 budget

$350,000

2023/24

2024/25

2025/26

2026/27

Subdivision Development Works

Subdivide City’s landholdings in Scarborough, Westminster and Yokine into individual residential lots for disposal

Q1 Engineering contractor appointed Q2 Subdivision works contractor appointed Q3 All clearances issued Project completed Q4

$Nil Budget carried forward

2023/24 budget

CORPORATE BUSINESS PLAN 2023-2027 | City of Stirling