Corporate Business Plan 2026-2030
Projects Carine Regional Open Space Community Parklands Upgrades – Stage 3 Complete the final stage of parkland upgrades, including new play equipment, accessible features, basketball half-court, shelters, seating and improved community facilities Commercial Redevelopment – 19 Roberts Road West Progress detailed design, approvals and tendering for the redevelopment of the site into a new commercial and industrial facility to support long-term economic outcomes 2026/27 budget
2026/27
2027/28
2028/29
2029/30
Q1 Q2 Works completed Q3
Q4
$1,100,000 Reserve funded
2026/27
2027/28
2028/29
2029/30
Q1 Conditional Building Premise Lease executed Q2 Development Application lodged
Q3
Q4 Construction contract awarded
2026/27 budget
$5,170,000 Reserve funded
2026/27
2027/28
2028/29
2029/30
InglewoodYouth Plaza
Design a dedicated youth recreation space at Wordsworth Reserve, including skate, basketball and informal social areas to support active and social use
Q1
Q2 Landscape consultant engaged
Q3 Design concept developed
Q4 Community consultation undertaken
2026/27 budget
$150,000
2026/27
2027/28
2028/29
2029/30
Land Subdivision
Undertake subdivision, approvals and initial works to enable the disposal of selected City landholdings and support future revenue generation
Q1 Q2 Subdivision plans developed
Q3 Council approval sought
Q4 Subdivision application lodged to WAPC
2026/27 budget
$1,300,000 Reserve funded