City of Stirling Corporate Business Plan
Outcome B2: Projects
2020/21
2021/22
2022/23
2023/24
Stephenson Avenue Extension
Q1
Phase 1: contract awarded Vegetation cleared Major earthworks completed
Design and construction of the extension of Stephenson Avenue 2020/2021 project cost: (funded by State and Federal government grants)
Q2 Q3 Q4
Drainage construction
Road construction Practical completion of Phase 1 achieved
2020/21
2021/22
2022/23
2023/24
West Coast Drive Cycling Improvements
Q1 Q2 Q3 Q4
Completion of design for works
To provide modifications to the configuration of West Coast Drive to provide a safer road environment for cyclists 2020/2021 project cost: $1,700,000
Completion of road resurfacing and kerb modifications
Mirrabooka Regional Improvement Strategy – Milldale Way road upgrade
2020/21
2021/22
2022/23
2023/24
Construction of Milldale Way between Mirrabooka Avenue and Chesterfield Drive 2020/2021 project cost: nil
2020/21
2021/22
2022/23
2023/24
Parking Management
Q1 Q2 Q3
To develop a strategy to improve the management of parking in the City including
within high demand parking areas 2020/2021 project cost: $40,000
Project commenced based on parking priorities as identified by Parking Working Group Scope development completed Consultant appointed Report completed and results presented at Parking Working Group meeting Project completed
Q4
2020/21
2021/22
2022/23
2023/24
Doubleview Commercial Centre
Design of the section of Scarborough Beach Road through the Doubleview Commercial Centre between Westview Street and Alice Street 2020/2021 project cost: Nil
Outcome B2: Infrastructure capital projects Program
Budget
Footpaths program
$1,750,000 $3,856,900
Rights of Way program Road renewal program
$6,612,000 Includes grant funding of $2,289,933
Other infrastructure renewals
$4,051,000 Includes grant funding of $332,000 + reserve funding of $556,000