City of Stirling Corporate Business Plan
Outcome B3: Projects
2020/21
2021/22
2022/23
2023/24
Hamersley Public Golf Course Redevelopment
Q1
Preparation of brief for engaging a design consultant commenced Tender for procuring design consultant commenced Community consultation undertaken
Stage 1 redevelopment of the Hamersley Public Golf Course into a vibrant modern facility providing a wide range of golf activities 2020/2021 project cost: $5,000,000
Q2 Q3 Q4
Design consultant engaged
Detailed design completed
Design documentation completed Tender ready for construction contract
2020/21
2021/22
2022/23
2023/24
Inglewood Oval and Hamer Park
Q1
Completion of tender design package and Community Sporting and Recreation Facilities Fund (CSRFF) grant fund application Procurement initiation and tender advertised for Hamer park and Moyle Pavilion Construction of oval lights to Inglewood Oval, Hamer Park east and west Results of CSRFF funding and contract award Completion of Oval lighting to Inglewood Oval, Hamer Park east and west Works for Moyle Pavilion and Hamer Park clubroom complete 45 per cent
Refurbishment and redevelopment of Moyle Pavilion and new construction of Hamer Park clubrooms 2020/2021 project cost: $556,812
Q2
Q3
Q4
2020/21
2021/22
2022/23
2023/24
North Beach Rugby League Facility Refurbishment
Q1
Detailed design and tender advertisement completed Tenders evaluated Preferred supplier submitted to Council for approval
Refurbishment of Charles Riley Clubroom 3 to improve the overall functionality of the facility 2020/2021 project cost: $700,000
Q2
Contract awarded and construction commenced
Q3
Construction completed
Q4
2020/21
2021/22
2022/23
2023/24
Bina Parkland Development
To create a new community hub at Bina Parkland in Balga 2020/2021 project cost: $2,137,555
Q1
Playground practical completion achieved BMX tracks, toilet, sump beautification, services and public amenities Practical Completion achieved
Q2
Skate park practical completion achieved
Q3 Q4
2020/21
2021/22
2022/23
2023/24
Precinct Packages
To improve the aesthetic and amenity of key precincts within the City of Stirling 2020/2021 project cost: $400,000
Q1
Precinct review completed and assessment of relevant achievable streetscape study actions also completed Preliminary works commenced
Q2
Commencement and scheduling of work by precinct
Q3
Continuation of work by precinct
Q4
Completion of work by precinct