Hamersley Public Golf Course Redevelopment

Q1

Preparation of brief for engaging a design consultant commenced Tender for procuring design consultant commenced Community consultation undertaken

Stage 1 redevelopment of the Hamersley Public Golf Course into a vibrant modern facility providing a wide range of golf activities 2020/2021 project cost: $5,000,000

Q2 Q3 Q4

Design consultant engaged

Detailed design completed

Design documentation completed Tender ready for construction contract

2020/21 

2021/22 

2022/23 

2023/24

Inglewood Oval and Hamer Park

Q1

Completion of tender design package and Community Sporting and Recreation Facilities Fund (CSRFF) grant fund application Procurement initiation and tender advertised for Hamer park and Moyle Pavilion Construction of oval lights to Inglewood Oval, Hamer Park east and west Results of CSRFF funding and contract award Completion of Oval lighting to Inglewood Oval, Hamer Park east and west Works for Moyle Pavilion and Hamer Park clubroom complete 45 per cent

Refurbishment and redevelopment of Moyle Pavilion and new construction of Hamer Park clubrooms 2020/2021 project cost: $556,812

Q2

Q3

Q4

2020/21 

2021/22 

2022/23 

2023/24

North Beach Rugby League Facility Refurbishment

Q1

Detailed design and tender advertisement completed Tenders evaluated Preferred supplier submitted to Council for approval

Refurbishment of Charles Riley Clubroom 3 to improve the overall functionality of the facility 2020/2021 project cost: $700,000

Q2

Contract awarded and construction commenced

Q3

Construction completed

Q4

2020/21 

2021/22 

2022/23 

2023/24

Bina Parkland Development

To create a new community hub at Bina Parkland in Balga 2020/2021 project cost: $2,137,555

Q1

Playground practical completion achieved BMX tracks, toilet, sump beautification, services and public amenities Practical Completion achieved

Q2

Skate park practical completion achieved

Q3 Q4

2020/21 

2021/22

2022/23

2023/24

Precinct Packages

To improve the aesthetic and amenity of key precincts within the City of Stirling 2020/2021 project cost: $400,000

Q1

Precinct review completed and assessment of relevant achievable streetscape study actions also completed Preliminary works commenced

Q2

Commencement and scheduling of work by precinct

Q3

Continuation of work by precinct

Q4

Completion of work by precinct